Cascade shows where one slip lands across every workstream, and the one action that matters.

See how Cascade works.

Select a workstream to see what it contributes to the project.

[DEMO] Piedmont Solar + StorageEquipment Procurement +30d

A procurement milestone moves 30 days.

Equipment Procurement10/16/26 +30dShifted
[DEMO] Piedmont Solar + StorageSOLAR+BATTERY9/24 done · 200 MW · COD 03/27/29Equipment Procurement +30d · 1 shifted
Anticipate

Equipment Procurement slipping 30 days to October 16 pushes commissioning and the ITC safe harbor placed-in-service timing right up against the wall; if procurement isn’t locked in before then, you risk losing the tax equity draw tied to the original in-service schedule and triggering delay penalties under the EPC contract. The single leverage point is the equipment order itself, not downstream construction scheduling. Re-issue and confirm the procurement PO by September 5, 2026 to keep the chain intact.

What’s now at riskCommercial Operation DatePPA Commercial Operations Date+60d

01Interconnection

6/10 done · 2 at risk

Interconnection request submi…09/26/24Done
Scoping meeting complete12/25/24Done
Phase I System Impact Study c…04/24/25Done
Decision Point I05/24/25Done
Phase II System Impact Study c…11/20/25Done
Decision Point II12/20/25Done
Phase III System Impact…06/18/2026At risk
Decision Point III06/18/2026At risk
Interconnection Servic…08/17/2026Pending
Network upgrades in-…03/27/2029Pending

02Permitting

2/4 done

Site Control09/26/24Done
Environmental review initiated12/20/25Done
Environmental Permit02/13/2027Pending
Use Permit / Zoning05/14/2027Pending

03Offtake

1/2 done

PPA term sheet executed06/23/25Done
Offtake / PPA Executed10/16/2026Pending

04Financing

0/3 done

Tax equity term sheet11/15/2026Pending
Construction loan com…01/14/2027Pending
Financing Close06/13/2027Pending

05Construction

0/5 done · 2 at risk

Equipment Procurement10/16/26 +30dShifted
EPC Contract Executed04/14/2027Pending
Construction Start07/13/2027Pending
Mechanical completion01/26/2029Pending
Commercial Operation…03/27/2029At risk

Cascade models a project as workstreams, with the dependencies between them stated outright.